Buyer checklist

Print this. Tick it on the roof, not in the shop.

Sabz Bijli and Solar Citizen publish installer checklists. Ours is the list we use against our own quote.

BEFORE MONEY

Paper

Written BOM: plate model + watts + Rs/W. Inverter model + PV input. Battery chemistry + usable kWh (DoD applied). Iron SWG. Cable mm² and jacket (XLPO). SPD, earth, labour. Not “5 kW package Rs 4 lakh.”

Flash report / serials for plates. CAN protocol named for LFP. Roof photo, shade, sanctioned load from the bill. Net-billing explained as export ≠ import.

WALK AWAY

Red flags

PERC 540 W “latest Longi.” 16 SWG stands. PVC “solar wire.” Four tubulars sold as night AC. On-grid-only on a 6-hour feeder without saying it dies. Green meter as a shop SKU. Unsigned cartons. Mixing MC4 brands. “1:1 net-metering still available” for a new file.

On the roof

14 SWG HDG or aluminium. Mid/end clamps torqued. No walking on glass. DC isolator labelled. Earth rod not a rusty nail.

On the wall

IP65 hybrid north/shade. Backup DB split. Battery CAN cable actually plugged. Dongle online before handover.

On handover

String Voc/Isc sheet. App login. Warranty serials. What is on backup vs not. DISCO file status if you wanted one.